FloQast’s ‘Work Through Calendar’ helps teams account for the extra working days sometimes needed to wrap up projects or the close by allowing holidays or weekends to be recognized as work days in the application. Adding dates to this calendar will activate the selected dates as potential working days and override holidays.
To utilize the Work Through Calendar, Admins will want to navigate to the Entities tab under Admin Settings, click the Manage button for the entity you wish to apply this to, and scroll to Calendar Settings:
Example:
In the Entity calendar settings, click to Add Work Through Day. You'll then see the space to name this calendar event and add the date. For example, if there is a weekend or holiday that needs to be used as a work through day, you can add it here so that it is included in your FloQast due dates calculations.